Remedial Basement Waterproofing to commercial structure
8 December 2021
Overview
Basement type: Refurbishment |
Building type: Residential |
Type of waterproofing: Type C |
Member: Delta Membrane Systems
|
Waterproofing design is a key and critical component for successful construction of below ground structures. Whether it’s a completely new build or making smaller changes to an existing property, waterproofing design should never be overlooked.
Waterproofing might account for just a small fraction of a building’s total cost, but waterproofing defects can result in catastrophic consequences. When waterproofing fails, the implications are significant.
Delta’s MD, Kevin Dodds was approached to offer advice and guidance on a failed waterproofing system.
The existing structure had an impressive 5-level basement which houses kitchens, food storage and food preparation areas, spa, plant rooms and accommodation. Near to a large river, the site sited well below the water table. The original waterproofing system was based on the secant piled walls and a block wall internally to provide a basic drained protection system with drainage holes at various points to drain to different levels.
Over time, the third floor had become completely saturated with all levels of the basement experiencing some degree of water ingress from damp patches to significant “jets” of water and flows of water through the secant piles.
With remediation waterproofing design strategies, it may take some time to specify a suitable system. It is important that investigations are thoroughly carried out by individuals with the capability of diagnosing the defect, assessing the extent of that defect, and recommending a suitable corrective measure.
Methodology
Following preliminary site inspections, discussions were held on remedial options, methodology for remedial works and cost. During site observations significant water was sitting behind the corbel. This water could be entering the structure either: directly through the piles, from the floor above or from the joint between the soffit and piles or a combination of all three.
When designing a robust waterproofing remediation approach, attention to detail is critical.
Balancing costs with quality, method suitability testing was carried out on trial areas. A combination of resin injections and curtain injection were proposed prior to the installation of a Type C cavity drain membrane system to facilitate performance levels. Alternative combinations were suggested on two trial areas.
Firstly, the secant piles were exposed and thoroughly cleaned to remove dirt, salts, and loose particles. Whilst slow flowing leaks and drips could be sealed with resin injections alone, any fast-flowing water ingress was stopped in advance of injection works with the use of Koster KD Blitz 2.
Koster 2 IN 1 was injected into the corbel area with Koster IN 7 being injected into the vertical joints between the piles.
It was observed following inspections, over a 5-week period, that the corbel area was dry. Delta’s MD, Kevin Dodds suggested a further monitoring period to assess performance levels.
Phase 1
Following trials and analysis of approach, Kevin suggested the use of Koster G4 Gel as a curtain injection to areas identified after exposure works to each area, in combination with Koster 2 IN 1 injection resin to the corbel detail. Each area would be injected and monitored for a period of 3 weeks prior to the installation of the Delta Type C cavity drain system.
To achieve a full belt and braces approach, further tweaks to the design would be incorporated as and when different degrees of water ingress were encountered or where concrete to the secant piles were particularly poor, this included increasing levels of the G4 salt accelerant to the G4 Gel to increase speed of reaction without compromising the ability to spread to create the “waterproof curtain” behind the piles in the area.
As the entire sub-structure was susceptible to hydrostatic pressure, the best approach to the 5-levels would be to work one level at a time, working downwards in sequence.
Phase 2
The principles of the Type C, cavity drain system were straightforward and typical of a multi-level basement. Additional design considerations were incorporated for detailing the corbel on which mid floor slabs required a careful approach. Kevin suggested increasing the number of downward drainage weepholes from upper to lower levels for continued access for maintenance, along with discharge points.
In addition to this approach, compartmentalisation of the cavity drainage system was required for fire safety.
Products used
- Koster IN 7
- Koster 2 IN 1
- Koster G4 Gel
- Koster KD2 Blitz
- Koster Waterstop
- Koster NB 1
- Koster Repair Mortar Plus
- Koster KB Flex 200
- Delta MS 500
- Delta MS 20
- Delta Drainage Channel
- Dual V3 Pumps, Alertmaxx 2 High level alarms
Results
When it comes to remedial waterproofing, a great waterproofing outcome requires expertise. This project has relied on bringing together an experienced team, from our partners at Koster UK to the main contractor, sub-contractor, and Delta Registered Installers who expertly installed the remedial solution.
The approach in this project has been one of open communication, commitment of shared goals and mutual trust.
The overall strategy, continuous trials, site monitoring and the ability to adapt the overall waterproofing design throughout the project have enabled completion of the works to date to an incredibly high standard with all parties confident of the positive and collaborative approach.